Metro Ph-2 being finalized ?

167

Written By Naveen - 24 January, 2010

Bangalore Route Namma Metro Media Reports BMRC Transportation public transport Metro Rail Phase2

A DH article dated 19-Nov-2009 stated that Metro Phase-2 would have two routes: one from Kathriguppe to ITPL, & the other from IIM-B to Nagawara. They would cover IIM-B, Jayadeva Hospital Circle, Dairy Circle, Vellara Junction, Old Airport Road, BEML, ITPL, Whitefield & Kattriguppe. The total length is about 55 km.

DMRC, as consultants are yet to finalise the financing model for phase II, & are working on three options: 100 per cent private funding (with a provision for the required viability gap funding), complete funding by government (both, Centre & State), & PPP (with government sharing civil works, with private partners taking charge of systems & operation).

If everything goes according to plan, work on phase II is slated to begin in mid 2010.

The combined (Phs 1 &2) routes according to this plan will appx'ly be as shown on the map below (click on it for biger image).

Metro Phase 2 -  Click for bigger image

COMMENTS


agara monorail

rackstar - 12 November, 2010 - 12:00

Majestic-Agara monorail was approved few months back, this maybe extended to electronic city. Monorail width is less so it can go parallel to BETL elevated highway.

Metro Phase 2

ashok_n - 10 November, 2010 - 05:48

Even after this Phase 2 gets built (whenever), there will be vast swathe of areas, South east of Bangalore which is not being covered. Right from Silkboard, E-City, Hosur Road, HSR layout, Sarjapur road, ORR, Bellandur etc which are not getting metro access. And these are the fastest growing areas.

 

  I read BYPL will be

idontspam - 10 November, 2010 - 10:21

  I read BYPL will be connected to EC without any details on the line

BYPL is already connected to EC at chandapura by commuter rail line. But of course, convenient truths will be overlooked by authorities for multicrore "truths"

Metro Phase2 news

vlnarayan - 9 November, 2010 - 22:16

Here's some news on Metro Phase2.

As per the news reported in DH, "The state Cabinet on Tuesday as cleared the revised estimate.
The second phase of the metro rail project covers 51 km. The second phase includes: connecting Mysore Road Terminal to Kengeri (7.7 km); Byapannahalli to ITPL (11.6km); Hesarghatta Cross - Bangalore International Exhibition Centre (4.20 km); Puttenahalli Cross - Anjanapura (6.7 km) and IIMB to Nagavara (21 km)."

www.deccanherald.com/content/111490/metro-govt-nod-revised-estimate.html

DPR seems to be already submitted as per news below, it will be interesting to see the route alignment from Byapannahalli to ITPL.

"The detailed project report has been submitted by the Delhi Metro Rail Corporation Ltd (DMRCL)."

sify.com/news/karnataka-okays-second-phase-of-bangalore-metro-news-national-kljxOkcidec.html

 

 

prioritize lines..

srinidhi - 10 November, 2010 - 01:14

 so its finally here..the phase II plans..ah not the plans its the approvals!!

anyways about what we have here:

  • Extension: Mysore Road Terminal to Kengeri (7.7 km);
  • Extension: Byapannahalli to ITPL (11.6km);
  • Extension: Hesarghatta Cross - BIEC (4.20 km);
  • Extension: Puttenahalli Cross - Anjanapura (6.7 km) 
  • New Line: IIMB to Nagavara (21 km)

Are these routes based on any justifications? Still dont understand why DMRCL has to do everything on planning for NM..dont we have the expertise or are we so dumb that we dont understand our traffic needs?

Of the four extensions, just the one connecting Byp to ITPL makes any traffic sense for now..

The other new line route (IIMB - Nagawara) needs to be seen..I am sure this will also need tweaking...that is if they allow it!

As mentioned in the reports they are getting on this simultaneously along with Phase I so we better hurry!

I am not able to put up a poll on praja..maybe my access does not allow..but it would be interesting to know opinions on how we can prioritize..based on the lines below:

  • Mysore Rd to Kengeri (7.7 km);Hesarghatta to BIEC (4.20 km);Puttenahalli to Anjanapura (6.7 km);IIMB to Nagavara (21 km);Byapannahalli to ITPL (11.6km);
  • Byapannahalli to ITPL (11.6km);IIMB to Nagavara (21 km);Hesarghatta to BIEC (4.20 km);Puttenahalli to Anjanapura (6.7 km);Mysore Rd to Kengeri (7.7 km);
  • Hesarghatta to BIEC (4.20 km);IIMB to Nagavara (21 km);Puttenahalli to Anjanapura (6.7 km);Byapannahalli to ITPL (11.6km);Mysore Rd to Kengeri (7.7 km);

 


PRAJA.IN COMMENT GUIDELINES

Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!