HOT TOPICS
SPOTLIGHT AGENCIES
Namma metro reach-1 tracker
Written By vinod_shankar - 1 August, 2009
Bangalore Namma Metro Citizen Reports Tracking Transportation public transport BMRCL Metro Rail Phase1
Objective tracking of namma metro from the data accumulated from the newsletter given out by BMRCL from feb 2009 upto july 2009 for reach-1. This will clearly give us trends on the progress of namma metro. I intend to update this data as and when new data is available. Here are the graphs.
Overall the reach-1 seems to chugging along to meet the december 2010 deadline. Also there is news that underground section has been awarded.
updated upto aug 09.
vinod
COMMENTS

blrsri - 1 August, 2009 - 11:58
Nice work Vinod..however ground realities makes it hard to accept the graph..
Its too linear for comfort!
They have fired a consultant.. they say..On site we can still see Navayuga ppl around! Moreover when one fires a consultant there is a trough expected in the progress!
CMH road is in a mess..with hardly anyworkers doing anything..
Ulsoor station work is also goin pain stakingly slow..please take a BMTC bus going towards majestic/market from OMR through ulsoor and you will see the 'progress'!
However I will try to pitch in with some regular photo updates..

tech - 2 August, 2009 - 04:45
Vinod, with your commitment on updating this site with Metro progress, We will bring back the old Metro tracking pages (remember, we had these for BIAL, BTRAC etc).
If more people can join Vinod here - we can collaborate for some nice community tracking of Bangalore Metro project. What you would have to do is very very simple.
- Visit BMRC website regularly
- Watch out for BMRC tenders in newspapers
- Take pictures once in a while if yo pass through Metro areas
- And, yes, do read the newspapers
And then, write Metro posts on praja 1-2 times a month, just make sure you use the right tags on the posts ("BMRC", "Namma Metro").
We will restore the Metro tracking page in a couple of days.

Thanks - need some clarifications
s_yajaman - 2 August, 2009 - 05:09
Vinod,
Thanks for putting this up.
Need to clarify terminology and the data itself for non civil engineers on this forum.
a. Piles - these are the foundations for the pillars
b. Pile caps - the concrete mat that rests on the piles. It looks like one pile cap for about 4 to 5 piles.
c. Piers - the vertical columns that support the load
d. Spans - the horizontal sections that rest on the piers on which the tracks are laid
e. Segments - trapezoidal sections that make up a span
Correct?
Your number are all cumulative.
At the rate at which they are progressing - assuming all goes well
a. All piles should be done in another 2 months - 61 piles at about 40 a month
b. Pile caps in another 4-5 months - 51 at about 10-12 a month
c. Piers - 6 months - 94 at about 15 a month
d. Spans - at the July rate - about 12 months.
Spans clearly are the bottleneck to progress. However if stretches are complete then I assume rails can be laid without waiting for the entire 7 km to be done.
Could you add the other parts as well if possible - rails, rolling stock, stations without which no trains can run.
Thanks again - this is good data based tracking.
Srivathsa

vinod_shankar - 4 August, 2009 - 13:53
thanks srivathsa for explaining the jargons....Yes the number are all cumulative. My hunch;observing the day to day progress, they will complete it much faster.
Some activities to be note regarding reach 1 are.
1.A part of the reach 1 contract has been offloaded to gammon india. Gammon india will be doing segment casting and launching from trinity to CMH road i guess.
2.Another set of launching trusses hasbeen put in place near old madras station by navayuga engineering, they should start launching segments from this end very soon.
3.As regards the stations, old madras station by IVRCL has showed good progress. Piers are already showing up. Piling work happening for trinity station by punj loyd. Working is slow at ulsoor station, which is one of the first stations were work was started.
yes will add rails, rolling stock stations as we go along. And BMRCL wants to lay tracks on the MG road stretch first and take up tracking laying as when stretches are complete of 1 km or more.

they don't respond to my queries
vinod_shankar - 8 September, 2009 - 07:48
@blrsri: Can i know to whom to you send the queries. they haven't responded to any of my queries raised below
http://praja.in/en/blog/vinod-shankar/2009/08/01/namma-metro-reach-1-tracker#comment-16896
vinod
PRAJA.IN COMMENT GUIDELINES
Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!