Presentation on CRS
Written By idontspam - 21 May, 2010
Prepare a presentation on CRS
COMMENTS

silkboard - 21 May, 2010 - 10:35
As we discussed yesterday, I have contacted Narayan for help with a solid and clear CRS map for Bangalore showing phase 1 focus routes, stations, new stations, and big catchment areas.
Need to be clear on what routes we are putting up in this presentation cum report. Lets do two, from this list
- Hebbal Anekal line - for sure, there is no Metro or Elevated road coming to cover the catchment areas here
- Yeshwantpur - Nelamangala (but they already have an elevated road coming there)
- Yeshwantpur - Devanahalli
Not that other lines are not important. But lets pick where chances of a competing proposal are lower (Metro, BRT etc), and there should be large catchment areas today or tomorrow.
Further, taking just 1 or 2 lines and detailing them will make for a better presentation than talking high level for the 9 tracks mentioned in CTTP.

working on the details for CRS bit busy in the office for next couple of days. Will prepare & will upload the details.
For Presentaion of CRS, we need to cover all the areas in few slides, but as you told we need to put routes with maximum coverage with more distance. CTTP has done short study with short distance coverage only, Local Train concept will work for more distance with maximum coverage. we should take the following root :
1 : Kengeri / Bidadi to Devanhalli 2. Yesvanthpur to Hosur 3. Kengeri Whitefiled / Bangarpet 4. Bangarpet to Devanahalli and Dodballpur via K R Puram
Do not take Yesvanthpur to Nelamanagala for presentation. Do not consider other infrastructure projects, we will concentrate on CRS.

What info is needed for CRS Report?
kbsyed61 - 21 May, 2010 - 14:49
Murali, blrsri, N, IDS and SB,
Thanks for all your efforts in materializing this meeting. It seems a very good meeting and that too with an action item.
I am very g;ad to note that we have already started on that path. Can one of you post a list of things or information that we should collect for preparing the report on CRS?
BTW what would be the objective of this report? I believe it should present the CRS infrastructure in a comprehensive manner.
I am sure it should have 3 components:
- Short Term - Improving the existing CRS service(YH) to make it purposeful
- Medium Term - Adding more routes on existing infrastructure
- Long Term - Plan for a consolidated CRS system that is well integrated with other PT system
Hope this is what we might have to work on.
As usual, my services are available for collecting info, drafting reports, presentations and follow up.
Syed

idontspam - 21 May, 2010 - 15:47
Pl check the presentation storyline attached with this task and provide feedback.

Sanjeev - 22 May, 2010 - 05:54
As per the meeting with IDD, do they want presentation or the proposal on CRS. As CTTP prepared by RITES did not consider the Devanhallai, Nelamangala, & Dodballapur and excluding KR Puram to Yelahanaka track.
MP Ananthkumar wants have full fledge discussion with presentation in ABIDe with BDA, BMTC, Railways, Traffic Commissioner, BMRCL, IDD with Chief Minister & MoS for State Railways K H Muniyappa.
As suggested @Syed
- First layout the comprehensive plan/proposal for CRS say how CRS will look like after 25 years.
- Plan that covers next 20-25 years - Routes, Features, Operation Options, Funding sources etc.
- From that plan, deduct medium term and near term feasibility/li>
- Near Term - Expand and improve the existing CRS service
- Medium Term - Introduce new routes with a minimum work on tracks, but lot of focus on new stops, amenities, integrating with other PT services
Here we should not get into the Financial aspect as IDD / Railway will do their work. Excpet funding of sources, these steps we should progress. Also we will not go into the details of capacity as this Railways subject, we will make point how existing DEMU / Passanger services to be converted into full fledge services of CRS and extending them in both directions.
As Syed told we have CRS in a small way running is true as the Train Number : YH1, YH-2, HY-1, HY-2, SD-1, DS-1, YD-1, DY-1, numbering of trains are meant for Local Trains only.
@Silkboard :
- Can some one detail all station connectivity needs with one example
- Can someone help with a list of stations needed on Hebbal-Anekal line?
We will not restric Hebbal-Anekal, we need to have list of new stations in all roots with explaining the importance of the location for ridership.
- Can some one do the cost analysis - how much would you possible charge for the ride?
Cost Analysis should be left to the Karnataka Govt & Railways. Instead of this we should suggest how each new station can be explored for commercial purpose as done in New Mumbai Stations.
Also project funding will be between State & Railways & our politicans will take call on that, we will not touch on this, We will provide the detail on how MMTS in Hyderabad, MRTS at Chennai, Suburban Trains at Mumbai were funded & operated.
Will upload the suggested roots for this CRS and current running DEMU / Passanger Trains arround Bangalore.
PRAJA.IN COMMENT GUIDELINES
Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!