HOT TOPICS
SPOTLIGHT AGENCIES
Shiradi Ghat Road
Written By tsubba - 24 January, 2008
Infrastructure Bangalore Mangalore
Minister,
Reality Part Ways On Shiradi Ghat
Source: Deccan Herald (Green
signal for expressway), The Hindu (Will
the Shiradi Ghat stretch be ready by June?)
The Hindu
Union Minister of State for Surface Transport K H Muniyappa assured
that the vexed Shiradi Ghat road improvement project will be completed
by May, before the onset of monsoon. The work is in full swing and the
project contractor has been directed to lay concrete stretches in
places prone to damage, he added.
However, Raviprasad Kamila of the hindu, reports tht it is unlikely the
road will be finished by June, the pace of repairs on this stretch of
the highway, taken up by the Mangalore Division of the National
Highways, does not seem to match the expectation.
The stretch of the highway passing through the ghat was closed for
heavy traffic three months ago to take up repairs. The authorities
concerned had promised that it would be reopened before the onset of
monsoon.
Curves
The main problem appears to be completion of the 13 critical curves
between Heggadde and Adda Hole Bridge. The curves are to get a facelift
with concrete stretch, at a cost of Rs. 8.42 crore.
Bhandarkar Constructions of Ujire, one of the contractors, is on the
verge of completing the work on only one side (vertical split) of the
eight curves. For this, the company has taken more than three-and-half
months. Besides completing the work on the other side of the eight
curves, the contractor will have to take up and complete both the
halves of the remaining five curves.
The completed work accounts for only 30 per cent of the contract.
An engineer supervising the work said that concrete was being laid in
three layers — 20 cm granular sub-base, 15 cm dry lean concrete and the
topmost 30 cm plain cement concrete.
The officials attribute the delay to use transit mixer (the one boarded
on a vehicle).
As far as road work is concerned, two contractors are working on
different patches of the 37-km ghat stretch simultaneously between
Durgamba Rice Mill near Sakaleshpur and Adda Hole Bridge near Gundya in
Dakshina Kannada district. One of them started the work in October
while the other started a month ago. A major part of the asphalting
work (22 km of the 37-km stretch) has been given to Durga Constructions
of Tamil Nadu. An official said that the company had enough manpower
and equipment, and expects that it would complete the work by March.
However, as one travels along the stretch, all he or she can see is
that only pothole-filling work has been taken up and not more than 20
people are working.
The contractor is expected to lay two fresh layers, known as dense
bituminous macadam (DBM) layer and bituminous concrete layer, after
filling the potholes.
S. Gopal, Executive Engineer of the division, told The Hindu that the
DBM layer would have thickness of 50 mm. On top of that 40-mm thick
bituminous concrete layer would be laid.
Mr. Gopal said that two more batches of workers were expected to arrive
shortly. “If you want to see the progress of work visit after a
fortnight,” he said. Durga Constructions is asphalting the stretch
between Heggadde and Adda Hole at a cost of Rs. 24 crore.
The other contracting company, Ramesh Kothari Constructions, which is
asphalting the 11-km stretch, has completed filling up potholes and is
laying the first of the two layers.
During a visit to the stretch between Durgamba Rice Mill and near
Heggadde (towards Mangalore) on Monday, it was found that work on about
3 km of the stretch up to Donigal was completed. The contractor has
promised to complete the work by the end of February. This contract was
awarded a cost of Rs. 5.37 crore.
Works in the ghat section are being done only during day time.
COMMENTS

Pratap Hegde - 28 January, 2008 - 07:08

tsubba - 23 April, 2008 - 14:10

The Roads Most Travelled - Gujarat Shows The Way
City.Zen - 7 May, 2008 - 11:41

mcadambi - 10 July, 2008 - 08:49
Read in "The Hindu" a day or two back that potholes have started emerging again in the Shiradi Ghat road because of overloaded Iron Ore lorries. The iron ore lorries which are supposed to carry 16 tonnes as an official limit now carry 45 tonnes. This iron ore and manganese ore come from Bellary thanks to the eminence grise of the Reddy brothers.
It is high time the Central Government bans the export of iron and manganese.

More money down the Shiradi Ghat drain
Transmogrifier - 11 February, 2009 - 21:49
What's hard to be believe is the ccountability standards (or rather the lack of them) here? I wonder how many crores it has cost the taxpayer to "fix" the Shiradi Ghat road. Do contracts/tenders like these have any language on the expected life of the road and liability of the the contractor if it fails to meet expectations? If they do, why are we paying for it...if they don't there has to be a way for it to be done. NHAI has made contractors liable for road works in Bangalore, GoK can easily do the same if the will exists.
TM
PRAJA.IN COMMENT GUIDELINES
Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!